Owner: Plano ISD, Plano, Texas
Architect: SHW Group, Plano, Texas
Completion: August, 2011
Contract Amt: $8,424,849.00
Contract Type: CM at Risk
Description: SRC constructed two classroom additions totaling 24,000 SF as well as an extensive renovation of the existing building in phases while school was in session.
Owner: Plano Independent School District,Plano, Texas
Architect: SHW Group, Plano, Texas
Completed: March, 2009
Contract Amt: $9,264,071.00
Contract Type: CM at Risk
Description: SRC constructed a 5,000 SF classroom and restroom addition with a 68,000 SF complete renovation of the existing building.
Owner: Plano I.S.D., Plano, Texas
Architect: Jacobs Facilities, Inc., Dallas, Texas
Completed: January, 2008
Contract Amt: $8,509,000.00
Contract Type: CM at Risk
Description: SRC constructed additions to the classrooms, kitchen, cafeteria, and administrative offices totaling approx. 23,000 SF and an extensive renovation of the 52,000 SF existing school building.
Project: Baxter Elementary School Additions and Renovations Midlothian, Texas
Owner: Midlothian I.S.D., Midlothian, Texas
Architect: VLK Architects, Arlington, Texas
Completed: August, 2007
Contract Amt: $3,240,075.00
Contract Type: CM at Risk
Description: SRC constructed two classroom additions totaling 12,000 SF and a 62,000 SF renovation to the existing facility.
Package: James Fannin Elem., School Maple Lawn Elem. and School Ben Milam Elem. School
Owner: Dallas I.S.D., Dallas, Texas
Architect: Shiver Associates Architects, Dallas, Texas
Completion Date: February, 2006
Contract Amount: $9,249,112.00
Contract Type: Stipulated Sum
Description: SRC constructed a 23,000 SF addition and completed a 68,000 SF renovation to Maple Lawn Elementary School. Also included was a 66,000 SF renovation to James Fannin Elementary School and 44,000 SF renovation to Ben Milam Elementary School
Owner: Plano I.S.D., Plano, Texas
Architect: Jacobs Facilities, Dallas, Texas
Completion: January 2007
Contract Amt: $9,194,422.00
Contract Type: CM at Risk
Description: SRC constructed a 28,000 SF two story science lab and a 6,500 SF band hall/team room addition as well as an 185,000 SF renovation. The renovation work was completed in stages during the summer and while class was in session.